EV Charging Fire Detection Design for Enclosed Car Parks | Finder

EV Charging Fire Detection Design for Enclosed Car Parks | Finder

Adding electric vehicle charging points to an enclosed car park is not simply a matter of adding a few detectors or charging units to an existing design. The vehicle battery, EVSE equipment and connections, distribution boards, smoke movement, safe charging shutdown, evacuation and fire-service response should be considered within one coordinated cause-and-effect strategy.

Isolating the charging supply stops charging through the EVSE, but it does not de-energise the vehicle traction battery. Fire safety for EV charging in enclosed car parks therefore requires detection, smoke control, water-based protection, power isolation and post-incident management to be planned together.

Four Sources, Four Design Questions

Source

Primary concern

Design question

Vehicle battery

Thermal runaway, vent gases and re-ignition

Where will smoke and heat develop, and how will they move through the car park?

EVSE, plug and cable

Local overheating, arcing, impact and connection faults

How is the fault detected and how is charging safely stopped?

Distribution board

Protection, selectivity and isolation

Which charging group is isolated, under what condition and by whom?

Ventilation / smoke control

Smoke dilution or redistribution

How do normal and fire modes affect detector response?

 

This approach is not an installation design. Final values should be verified against current legislation, adopted standards, manufacturer instructions, the approved fire strategy and competent engineering calculations.

1. Start with the Existing Car-Park Fire Strategy

Before EV charging infrastructure is added, the existing fire-safety baseline of the car park should be documented. Area, basement level, sprinkler and fire-water provisions, mechanical smoke control, existing fire alarm zones, escape routes, fire-service access and electrical distribution should be reviewed together.

The new charging project should identify which parts of the existing strategy change. Charging areas should be clearly represented in the fire alarm system and graphics, while charging groups and feeder boundaries should be defined in the cause-and-effect strategy.

For projects in Türkiye, the current Binaların Yangından Korunması Hakkında Yönetmelik and relevant administrative guidance should be checked. The source document states that Article 60 includes key provisions for enclosed car parks, including automatic sprinkler/fire-water measures above 600 m² and independent mechanical smoke exhaust above 2,000 m². Local authority and project-specific requirements should also be verified.

The source also states that the Regulation contains no provision specific to EV charging stations and that a Ministry opinion letter dated 23 January 2026 considers compliance with the fire measures of the Regulation sufficient for charging stations. This interpretation should be checked in its current form for the actual project.

2. Detection Architecture Should Not Depend on a Single Sensor

Point smoke, heat or multi-criteria detectors; beam or aspirating systems; thermal monitoring; gas/VOC sensing and EVSE/EMS telemetry can serve different functions in an enclosed car park. They are not direct substitutes for one another.

Smoke detection may provide early response, but exhaust, dust and airflow should be considered because of nuisance-alarm risk and response time. Heat or multi-criteria detection may suit some contaminated environments, although response may be later.

Beam or aspirating detection may be considered for large or unusual ceiling geometries. Beams, fans, obstructions and maintenance access should be taken into account. Thermal monitoring can provide supplementary warning, but line of sight and alarm thresholds remain important.

Gas or VOC sensing may provide an early indication in some battery venting events. Because battery chemistry, ventilation and sensor selectivity vary, it should not be treated as a universal fire-detection method.

EVSE or energy-management signals such as overtemperature, leakage, fault or charging state may also provide useful technical information. Signal meaning, failsafe behaviour and response to communication faults can vary by manufacturer.

3. Layout, Zoning and Access Should Be Planned Together

Charging bays should be coordinated with escape routes, pedestrian paths, columns, sprinkler heads, hose cabinets and responder access. Instead of showing only loop and device numbers, addressable labels such as “B2 – EV Charging Bank A” can make incident management easier.

Access to detectors and manual call points should not be obstructed by EVSE impact protection, cable trays or vehicle movement. Detector positions should be reviewed together with supply and extract grilles, jet fans, beams and ceiling pockets.

A manual fire alarm point, EVSE emergency isolation and the fire alarm control panel do not serve the same function. Each should be clearly identified on site. Where graphics or remote monitoring are used, the event message should clearly show the floor, charging bank and isolation scope.

4. Cause-and-Effect Should Define the Path from Alarm to EVSE Isolation

The main integration question is which input operates which output, with what delay and with what reset authority. Where the approved design requires it, a confirmed fire alarm may isolate a defined EVSE group. This action stops the charging supply only; the vehicle traction battery remains on the vehicle.

A confirmed fire alarm may initiate occupant warning, remote notification and shutdown of a selected EVSE group. The isolation scope, latching and reset authority should be clearly defined.

A sprinkler flow signal or approved fire scenario may affect smoke control, EVSE isolation and event transmission. The approved sequence and timing should be preserved.

An EVSE overtemperature or critical fault signal may stop charging and create a technical alarm. Not every EVSE fault is a building fire alarm. Signals should be clearly classified as fire, technical fault or pre-warning.

Manual emergency isolation may disconnect the defined EVSE supply. Unauthorised re-energisation should be prevented and the function clearly labelled. Fan faults may be reported to the fire alarm panel or BMS, and the emergency strategy should consider actual fan status.

5. Ventilation and Smoke Control Change Detector Response

Mechanical ventilation can dilute smoke, move it away from a detector or carry it into another zone. Detection should therefore be assessed under both normal ventilation and fire-mode operation.

Where jet fans or mechanical smoke control are used, alarm zones and fan-control zones should be coordinated. Normal and fire modes may produce different detector response times.

High air velocity near a grille can delay local smoke accumulation. Detector placement should be checked against the spacing rules of the adopted standard and manufacturer instructions. If a fan fails, actual smoke movement may differ from the design condition; the fault should therefore be monitored and the system response defined.

The sprinkler and ventilation sequence is another coordination issue. Because airflow may affect activation dynamics, the final sequence should be verified through the approved fire strategy and commissioning tests.

6. Suppression, Responder Access and Post-Fire Management

A fire detection system does not extinguish battery thermal runaway. Lithium-ion battery events may continue to generate heat and may re-ignite after initial suppression. Water-based protection, fire-service access, water supply, drainage, contaminated run-off management, smoke control and post-fire vehicle monitoring/removal should therefore be considered together.

The scope, duration and fire-spread objective of water-based protection should be verified against applicable requirements and the approved fire strategy.

Responders should be able to identify the fire alarm panel, EV isolation point and charging area quickly. Drainage and management of potentially contaminated run-off should consider the possibility of extended water application.

A post-fire monitoring and safe vehicle-removal procedure should be established. Portable extinguishing equipment should be selected for incipient non-battery fires according to the risk assessment.

7. What Should Be Verified During Design Review?

Before the design is finalised, the existing car-park fire strategy, zoning and as-built records should be reviewed. EVSE locations should be coordinated with escape routes, fire-service access, sprinklers and smoke control.

Charging-group feeders and isolation boundaries should be defined, while detector technology and placement should be checked against ceiling geometry, beams and airflow. EVSE/EMS signals should be classified as fire, technical fault or pre-warning.

The cause-and-effect matrix should include alarms, fans, notifications, doors and charging shutdown. The manual isolation point, authority and re-energisation procedure should be documented. Fire-service information should clearly identify EV charging areas and isolation controls.

Post-fire battery monitoring and vehicle recovery should be included in the emergency plan, and commissioning tests should cover both normal and fire-mode ventilation.

8. Main Functions to Test During Commissioning and Maintenance

Test / maintenance item

Expected evidence

Detector alarm, pre-alarm and fault

Address/zone, timestamp and panel message

EVSE critical fault / technical alarm

Signal class, protocol and fire/BMS response

Automatic EVSE isolation

Affected bank, delay, latch and reset authority

Manual emergency isolation

Location, label, access and actual disconnection

Smoke control / fans

Normal/fire mode, feedback and fault status

Sprinkler / fire-scenario interface

Flow/supervisory signal and cause-and-effect output

Remote monitoring / security desk

Correct floor, charging bank and event class

Documentation

As-built, I/O list, matrix, test records and revision history

 

Acceptance should not end when devices produce an alarm. The roles of security, technical and management teams in alarm, isolation and evacuation should also be verified through scenario testing.

9. Frequently Asked Questions

Does every EV charging bay need a dedicated detector?

No, not as a universal rule. Detector type, quantity and position should be determined from the adopted standard, ceiling geometry, airflow and documented risk assessment.

Should smoke or heat detection be used?

There is no single answer. Smoke detection may provide earlier warning, while exhaust, dust and airflow can increase nuisance-alarm risk. Heat or multi-criteria detection may be considered according to environmental conditions.

Should EVSE alarms be connected to the fire alarm system?

Selected manufacturer signals may be integrated as supplementary technical alarms. Each signal should be clearly classified and tested as fire, technical fault or pre-warning.

Should charging power automatically shut down on a fire alarm?

It may, where the approved cause-and-effect strategy requires it. The isolation scope, delay, latching and reset authority should be defined.

Does isolating the EVSE de-energise the vehicle battery?

No. Disconnecting the charger or its supply stops charging, but the vehicle traction battery remains installed and may remain energised.

Can enclosed-car-park ventilation affect detectors?

Yes. Fans may dilute or relocate smoke. Detection should be assessed and tested under both normal and fire ventilation modes.

Can thermal imaging replace a fire detector?

Generally no. Thermal monitoring can provide supplementary temperature warning; replacement of the fire-detection function requires verification under the adopted standard and approved fire strategy.

Is the risk over once an EV fire is suppressed?

Not always. Lithium-ion batteries may re-ignite. Post-fire monitoring, a safe holding location and a vehicle-removal procedure should be planned.

What basic legislation should be checked for enclosed car parks in Türkiye?

The current Binaların Yangından Korunması Hakkında Yönetmelik, relevant administrative guidance, electrical-installation requirements, local fire-authority conditions and the standards adopted for the project should be verified together.

Conclusion

EV charging infrastructure in an enclosed car park requires fire safety and electrical engineering to be considered together. A robust design combines detection and zoning, smoke control, selective EVSE isolation, water-based protection, notification, evacuation and responder access in one testable cause-and-effect plan.

The approach should not rely on one detector rule, but on a risk-based and verifiable design. After handover, the system should continue to be managed through maintenance, change control and emergency procedures.

Sources

•  Binaların Yangından Korunması Hakkında Yönetmelik (Türkiye) — özellikle Madde 60, kapalı otopark hükümleri: https://www.mevzuat.gov.tr/

•  T.C. Çevre, Şehircilik ve İklim Değişikliği Bakanlığı, Yerel Yönetimler Genel Müdürlüğü — Görüş: Elektrikli araç şarj istasyonlarının ruhsatlandırılmasında aranan yangın tedbirleri hk., 23.01.2026 tarihli ve E-14399437-045.02-14291808 sayılı yazı (12.02.2026 tarihinde yayımlanan nüsha): https://webdosya.csb.gov.tr/v2/yerelyonetimler/2026/02/Elektrikli-ara-arj-ist-20260212172424.pdf

•  IEC 60364-7-722:2018 — Low-voltage electrical installations, Supplies for electric vehicles: https://webstore.iec.ch/en/publication/29958

•  IEC 61851-1:2017 + COR1:2023 — Electric vehicle conductive charging system, General requirements: https://webstore.iec.ch/en/publication/33644

•  UK Office for Zero Emission Vehicles — Covered car parks: fire safety guidance for electric vehicles (published 2023, updated 08.02.2024): https://www.gov.uk/government/publications/covered-car-parks-fire-safety-guidance-for-electric-vehicles

•  EN 54 series — Fire detection and fire alarm system component standards; applicable parts and current editions to be verified for the selected architecture.

 

Other Blog Posts